KABELI-A: World Bank Is Back

After pulling out from Arun III in 1995, the World Bank Group has decided to support Kabeli-A Hydroelectric Project

May 23, 2014, 5:45 p.m. Published in Magazine Issue: Vol: 07 No. -22 May. 23- 2014 (Jestha 9, 2071)

With over 12 hours of power outage, Nepal’s energy crisis is creating a lot of problems. As Nepal government is seeking foreign investment in hydropower, the decision of the World Bank Group to finance Kabeli-A has significant implications.

After the bank pulled out from Arun III, this is the first hydropower project it has approved. Moreover, the decision came when Dr. Ram Sharan Mahat, who was one of the die-hard supporter of Arun III, is leading the Finance Ministry.

As the demand for power in the eastern grid of Nepal is increasing, the construction of Kabeli A will provide additional energy to the grid which is now relying heavily on the electricity generated in western, central India.

Along with Kabeli A, a number of middle scale hydropower projects are under construction in eastern Nepal with over 100 MW power generating capacity. Maikhola 22 MW with 7 MW casket Hydropower project is close to completion as are Puwakhola 4, Upper Mai 15 and Hewa 15.

The World Bank Group approved financing of US$ 84.6 for the Kabeli-A Hydroelectric Project.  The financing includes a US$ 40 million credit and a US$ 6 million grant from the International Development Association (IDA) and a US$ 19.3 million loan from the International Finance Corporation (IFC).  Additionally, the package includes a US$ 19.3 million loan from the Canada Climate Change Program (CCCP) for which the IFC acts as the implementing agency.

Kabeli-A is a peaking run-of-river hydroelectric project with an installed capacity of 37.6 MW.  It will be built in Panchthar district in the eastern hills of Nepal.  The energy output will be connected to the national grid via the Kabeli Corridor Transmission Line, a separate project under construction with World Bank financing.  Kabeli-A was among the projects shortlisted in the late 1990s on the basis of a screening and ranking exercise. 

Following an International Competitive Bidding process in 2007, the Government of Nepal offered the contract on Build, Own, Operate and Transfer (BOOT) terms to Kabeli Energy Ltd.  Kabeli Energy Ltd. will invest US$ 23 million towards the US$ 108.6 million cost of the project.

“Reliable electricity is central to any modern economic infrastructure,” said Johannes Zutt, World Bank Country Director for Nepal. “No country has achieved middle-income status without ensuring access to reliable, sustainable and affordable modern energy. This World Bank-IFC project will demonstrate how public-private partnerships can help Nepal exploit its hydropower potential and eliminate electricity deficits while also developing hydroelectricity exports as an engine of the nation’s economic growth.”

According to a press release issued by the World Bank, the project has three components.  Kabeli Energy Ltd. will implement the first component to build plant infrastructures including a diversion dam, a settling basin, a headrace tunnel, a semi-underground powerhouse, and a tailrace tunnel. 

The second component will support the Ministry of Energy in supervising implementation of the project in compliance with technical, environmental and social safeguards and to improve its capacity in overseeing hydropower development.  The third component will support the Investment Board of Nepal in improving its ability to facilitate the development of large hydropower projects in line with applicable international technical, environmental, social and performance standards.

“The project design reflects the lessons learned from hydropower projects worldwide, including those in the Himalayas where similar conditions exist,” said Jie Tang, World Bank Lead Energy Specialist and Task Team Leader for the project.  “The lessons suggest avoiding delays in project preparation and implementation, improving social and environmental management, enhancing sediment handling capacity, and improving the long term sustainability of the project.

More on National

The Latest

Latest Magazine

VOL. 17, No. 17, April.12,2024 (Chaitra,30. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 17, No. 16, March.29,2024 (Chaitra,16. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 17, No. 15, March.10,2024 (Falgun,27. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 17, No. 14, February.23,2024 (Falgun,11. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75