Upper Trishuli 3 B: Construction Work Resumed

After 14 months, the construction work of Upper Trishuli 3 B project resumed

April 26, 2021, 7:11 p.m.

Working quietly and carefully, Mohan Prasad Gautam, Managing Director of Trishuli Jal Vidhyt Company Limited, has a sigh of relief this week following the resumption of the project mobilizing the workers in the project site.

For the past 14 months, managing director Gautam, who also has experienced working in Upper Tamakoshi Project, had a very hectic time facilitating and coordinating with different authorities to resume the work which was disrupted due to COVID-1.

With the so many risks involved due to covid-19, MD Gautam has to work very cautiously. In the first few months, Chinese contractors trapped in China. Following March, the shutdown of air service disrupted.

Finally the contractor the construction work of the Upper Trishuli 3 B hydropower project has resumed work from April 26. Given the growing incidents of COVID-19, the threat still looms large.

p3.jpg

With a capacity of 37 MW, Upper Trishuli 3 B Project is a cascade project of the Upper Trishuli 3 A project.

The project work stopped following the Chinese workers, who left for their country in December 2019 to celebrate the Chinese New Year, did not return to the project due to the surge of coronavirus in China. It was virtually a standstill for the 14 months due to covid-19 and stalling of the equipment in the border.

The contract of the project was awarded to Sichuan (AANHE Hydroelectric Engineering of China. Maintaining the strict health protocol, the contractor has resumed its work now in the main tunnel, powerhouse and other structures,” said Mohan Prasad Gautam, managing director Trishuli Hydropower Limited, project. He said that there are 64 Chinese and 81 Nepalese workers working at the construction site.

“After continuous efforts effort from our side, we are able to resume the stalled construction work bringing back all the workers,” he said. He also said that the project is facing difficulties to transport the construction equipment and materials, which are purchased and some in the packaging and production stage, to the project site in Nepal due to the shut down of the Nepal-China border. If this disruption continues, it will likely affect the resumption of construction work. We have been coordinating with the Ministry of Energy, Water Resources and Irrigation and various offices of the Ministry of Finance. Constructed under the People’s Electricity Program, the 37 MW Upper Trishuli 3 B project situated in Rasuwa and Nuwakot district has started aimed to complete by March 2020.

With the disruption in construction for 14 months' inability to work this winter, the project completion date has postponed to 2023 April. Under the Engineering Procurement and Construction (EPC) model, the Chinese contractor HNHE Hydroelectric and Engineering signed an agreement with the company at the cost of Rs. 1.91 billion (30.19 Million US $) in 2074 Magh 29.

The contractor company is responsible for the construction of all civil, electric and hydro-mechanical work. The company also designs equipment, construction and installation. The physical progress of the project at present is 47 percent.

p3.jpg

Prime Minister KP Sharma Oli his wife Radhika Oli and then Energy minister Barshaman Pun Purchased 20/20 each share of the promoter of the project Trishuli Hydropower Company Ltd.

Prime minister Oli purchased the share during the issuance of 3.7 million shares to the public. Out of the 3.8-kilometer tunnel, the 1.8-kilometer tunnel has already constructed and the progress work of powerhouse construction and support work has 76 and 35 percent respectively.

As a cascade project of 60 MW Upper Trishuli 3 A project, there do not need not to construct disender pond and the gate at the headwork has already been completed. The construction work of box culvert has already begun.

Nepal Telecom and Nepal Electricity Authority (NEA) has30/30 promoter share in Trishuli Hydropower Company Limited. Rural Municipality, Municipality each has 5 percent share, local financial institution of Rasuwa and Nuwakot has 5 percent, and local residence of Rasuwa and Nuwakot has 10 percent, public 15 and employee of NEA and Telecom 5 percent each.

With the estimated cost of Rs.7.44 billion with a projected interest of Rs.780 million, the project generation capacity will be 134.8 million units during the winter and 157.7 million units. The power will be evacuated through 3-kilometer long transmission line Trishuli 3 B hub stations.

Although MD Gautam has a sigh of relief now, one cannot rule out the possibility of disruption in the coming days given the second phase of the COVID-19 spike in Nepal.

p6.jpg

More on Economy

The Latest

Latest Magazine

VOL. 17, No. 17, April.12,2024 (Chaitra,30. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 17, No. 16, March.29,2024 (Chaitra,16. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 17, No. 15, March.10,2024 (Falgun,27. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75

VOL. 17, No. 14, February.23,2024 (Falgun,11. 2080) Publisher and Editor: Keshab Prasad Poudel Online Register Number: DOI 584/074-75